Works value £100,000
Ground stabilisation following local de-forestation, to avoid possible land slippage
Re-grade the moorland face and support the gradient with gabion baskets, backfill with local granite stone
All works carried out by HFN team of specialist hardworks operators using 15 tonne 360° HFN excavators